IPSWICH
CITY
COUNCIL
AGENDA
of the
AGENDA
Infrastructure, Planning and Assets Committee
Tuesday, 11 June 2024
9.00 am
Council Chambers, Level 8
1 Nicholas Street, Ipswich
MEMBERS OF THE Infrastructure, Planning and Assets Committee |
|
Councillor Andrew Antoniolli (Chairperson) Councillor Paul Tully (Deputy Chairperson) |
Mayor Teresa Harding Deputy Mayor Nicole Jonic Councillor David Cullen Councillor Jim Madden |
Infrastructure, Planning and Assets Committee Meeting Agenda |
11 June 2024 |
Infrastructure, Planning and Assets Committee AGENDA
Item No. |
Item Title |
Page No. |
|
Welcome to Country or Acknowledgment of Country |
|
|
Declarations of Interest |
|
|
Business Outstanding |
|
|
Officers’ Reports |
|
1 |
Proposed Ipswich Adopted Infrastructure Charges Resolution (No 1) 2024 |
7 |
2 |
**River Heart - Proposed Removal of Over-Water Structures |
81 |
3 |
Springfield Central E-Scooter Pilot |
98 |
4 |
Asset and Infrastructure Services Department Capital Delivery Report April 2024 |
128 |
5 |
Planning and Environment Court Action Status Report |
154 |
6 |
Exercise of Delegation Report |
159 |
|
Notices of Motion |
|
|
Matters Arising |
|
** Item includes confidential papers
Infrastructure, Planning and Assets Committee NO. 2024(01)
11 June 2024
AGENDA
Welcome to Country or Acknowledgement of Country
DECLARATIONS OF INTEREST IN MATTERS ON THE AGENDA
BUSINESS OUTSTANDING
Officers’ Reports
1. Proposed Ipswich Adopted Infrastructure Charges Resolution (No 1) 2024
This is a report concerning the adoption of the proposed Ipswich Adopted Infrastructure Charges Resolution (No. 1) 2024 to replace Council’s current charges resolution, the Ipswich Adopted Infrastructure Charges Resolution (No. 1) 2023. This is an annual exercise to ensure that Council’s charges for trunk infrastructure keep pace with increases in infrastructure costs, by applying the Producer Price Index (PPI) for Construction.
Recommendation
That Council adopt the proposed Adopted Infrastructure Charges Resolution as detailed in Attachment 1 pursuant to s113 of the Planning Act 2016 as the Ipswich Adopted Infrastructure Charges Resolution (No. 1) 2024.
2. **River Heart - Proposed Removal of Over-Water Structures
This is a report concerning repeated damage sustained to the overwater structures within River Heart following the 2022 and 2024 flood events and the recommendation for Council to remove the overwater structures as part of the site’s full recovery. The overwater structures are degrading with each flood event with increased ongoing financial costs to Council to continue to restore the structures.
Recommendation
A. That Council approve the removal of the overwater structures as detailed on page 2 of this report.
B. That Council note that the western deck will be retained which provides protection and housing for the irrigation pump and associated infrastructure.
3. Springfield Central E-Scooter Pilot
This is a report concerning the electric scooter (e-scooter) pilot scheme which is being held in the Springfield Central area. In particular, the report discusses the pilot to date and the proposal to extend the pilot to enable collection of additional data to support Council’s future position for micro-mobility devices across the City.
Recommendation
A. That the report be received and the contents noted.
B. That Council approve the extension of the current e-scooter pilot in Springfield Central area for an additional 12 months to 1 July 2025, with the option for an additional 12 month extension if considered necessary.
4. Asset and Infrastructure Services Department Capital Delivery Report April 2024
This is a report concerning the performance of the capital delivery by the Asset and Infrastructure Services Department for the month of April 2024.
Recommendation
That the report on capital delivery by the Asset and Infrastructure Services Department be received and the contents noted.
5. Planning and Environment Court Action Status Report
This is a report concerning a status update with respect to current court actions associated with development planning applications.
Recommendation
That the Planning and Environment Court Action status report be received and the contents noted.
6. Exercise of Delegation Report
This is a report concerning applications that have been determined by delegated authority for the period 3 May 2024 to 27 May 2024.
Recommendation
That the Exercise of Delegation report for the period 3 May 2024 to 27 May 2024, be received and the contents noted.
NOTICES OF MOTION
MATTERS ARISING
Infrastructure Planning and Assets Committee Meeting Agenda |
11 June 2024 |
ITEM: 1
SUBJECT: Proposed Ipswich Adopted Infrastructure Charges Resolution (No 1) 2024
AUTHOR: Senior Planning Officer (Strategic)
DATE: 24 May 2024
This is a report concerning the adoption of the proposed Ipswich Adopted Infrastructure Charges Resolution (No. 1) 2024 to replace Council’s current charges resolution, the Ipswich Adopted Infrastructure Charges Resolution (No. 1) 2023. This is an annual exercise to ensure that Council’s charges for trunk infrastructure keep pace with increases in infrastructure costs, by applying the Producer Price Index (PPI) for Construction.
That Council adopt the proposed Adopted Infrastructure Charges Resolution as detailed in Attachment 1 pursuant to s113 of the Planning Act 2016 as the Ipswich Adopted Infrastructure Charges Resolution (No. 1) 2024.
RELATED PARTIES
The proposed Adopted Infrastructure Charges Resolution (AICR) is relevant to persons who pay levied charges towards Council’s trunk transport, parks and land for community facilities infrastructure, related to their development approvals and also to Urban Utilities who levy charges for trunk water supply and wastewater infrastructure.
ifuture Theme
Vibrant and Growing
A Trusted and Leading Organisation
Purpose of Report/Background
The Ipswich Adopted Infrastructure Charges Resolution (No. 1) 2023 (current charges resolution) came into effect on and from 3 July 2023 pursuant to s113 of the Planning Act 2016 (the Act).
The infrastructure charges rate included in the current charges resolution are based on rates applicable as at 31 March 2023 and require indexation, by applying the PPI for Construction, to keep pace with increases in infrastructure costs as provided for in the Act.
It is proposed to index Council’s trunk infrastructure network charges to reflect the increase in costs over the twelve (12) month period to 31 March 2024 pursuant to the Act.
The proposed changes
The proposed infrastructure charges contained in Schedule 2 of the proposed AICR have been indexed consistent with the requirement of the Act to use the PPI for Construction (6427.0 Index Number 3101 - Road and Bridge Construction Index for Queensland). This equates to an indexation increase of 6.29% (indexation factor of 1.0629) for the twelve (12) month period.
The increase will only apply if the total charge levied is equal to or below the State government’s prescribed amount (maximum charge) pursuant to both the Act and the Planning Regulation 2017 (the Regulation) as calculated pursuant to the resolution. These changes are outlined in Attachment 1.
It is proposed that the new AICR, including the increased charges, apply on and from 1 July 2024, and that the AICR be uploaded onto Council’s website on that date.
Legal IMPLICATIONS
This report and its recommendations are consistent with the following legislative provisions:
Planning Act 2016
Planning Regulation 2017
policy implications
This is an annual process, there are no other relevant policy implications.
RISK MANAGEMENT IMPLICATIONS
The proposed indexation of infrastructure charges is consistent with the Act and the Regulations.
The infrastructure charges that may be levied on development pursuant to the proposed AICR cannot exceed the prescribed amount in the Regulation and are generally considered an industry standard.
As identified in the supporting material to the Council’s Local Government Infrastructure Plan (LGIP), the trunk infrastructure network is not able to be completely funded by infrastructure charges revenue with the gap between the cost and revenue increasing. This shortfall would be exacerbated if infrastructure charges are not appropriately indexed as provided for by adopting the proposed AICR.
Any such shortfall would need to be supplemented by other general revenue, grants or subsidies.
Financial/RESOURCE IMPLICATIONS
The proposed indexation of the infrastructure charges tables pursuant to the Act ensures that infrastructure charge continues to more closely reflect construction industry pricing increases.
No additional resources are required to give effect to the proposed AICR which is proposed to be undertaken by the City Design Branch.
COMMUNITY and OTHER CONSULTATION
No consultation is required to be undertaken pursuant to the Act. It is proposed that the new AICR be uploaded onto the Council website and an eAlert issued upon adoption to inform subscribers of the service.
The indexed infrastructure charge tables will be provided to Urban Utilities for inclusion in the Charges Schedule of the Urban Utilities’ Water Netserv Plan.
Conclusion
It is recommended that the proposed AICR be adopted as detailed in Attachment 1 which incorporates the indexed infrastructure charges, with the proposed AICR to come into effect on and from 1 July 2024.
HUMAN RIGHTS IMPLICATIONS
HUMAN RIGHTS IMPACTS |
|
OTHER DECISION |
|
|
|
(a) What is the Act/Decision being made? |
The adoption of the Ipswich Adopted Infrastructure Charges Resolution (No. 1) 2024 pursuant to s113 of the Planning Act 2016. |
(b) What human rights are affected? |
Human Rights are not affected by this decision. |
(c) How are the human rights limited? |
Not applicable.
|
(d) Is there a good reason for limiting the relevant rights? Is the limitation fair and reasonable? |
Not applicable. |
(e) Conclusion |
The decision is consistent with human rights. |
Attachments and Confidential Background Papers
1. |
Ipswich Adopted Infrastructure Charges Resolution (No 1)
2024 ⇩ |
Richard de Vries
Senior Planning Officer (Strategic)
I concur with the recommendations contained in this report.
Garath Wilson
Strategic Planning Manager
I concur with the recommendations contained in this report.
Brett Davey
General Manager (Planning and Regulatory Services)
“Together, we proudly enhance the quality of life for our community”
Infrastructure, Planning and Assets Committee Meeting Agenda |
11 June 2024 |
ITEM: 2
SUBJECT: River Heart - Proposed Removal of Over-Water Structures
AUTHOR: Program Manager (Flood Recovery CFRCP)
DATE: 31 May 2024
Executive Summary
This is a report concerning repeated damage sustained to the overwater structures within River Heart following the 2022 and 2024 flood events and the recommendation for Council to remove the overwater structures as part of the site’s full recovery. The overwater structures are degrading with each flood event with increased ongoing financial costs to Council to continue to restore the structures.
Recommendation/s
A. That Council approve the removal of the overwater structures as detailed on page 2 of this report.
B. That Council note that the western deck will be retained which provides protection and housing for the irrigation pump and associated infrastructure.
RELATED PARTIES
There was no declarations of conflict of interest.
ifuture Theme
Vibrant and Growing
Purpose of Report/Background
River Heart was constructed and officially opened in 2007. Since the opening of the site, River Heart has experienced a minimum of seven (7) flood inundations from minor to major flood level events. This means this site, specifically the overwater structures are experiencing on average, a flood inundation every two years.
The repeated flood inundation to the overwater structures is causing continued degradation and increased ongoing costs to recover and restore the structures. Due to their low-lying positions, the overwater structures will always be susceptible to flood inundation particularly low or minor level flooding.
Following the 2011 flood event the cost to recover this site and return it back to full activation for the community was in the order of $1 million. With weather events such as flood events becoming more frequent the future recovery of this site following flood inundation is expected to exponentially increase in costs.
Potential funding from the state for future flood or declared events for locations such as River Heart, which are positioned on the river, may not be guaranteed or available in the future. Sites such as these are not considered essential assets, and if no funding is provided, it would be a cost that Council would need to wholly absorb following any flood event.
Anecdotally, in recent years, the parkland is used primarily for exercise, and as a thoroughfare linking River Heart to the Bob Gamble site via the pathways, with the existing overwater structures used rarely.
Following the February and May 2022 flood events Council advertised for tenders from suitable contractors to undertake repairs and restore the overwater structures but was unsuccessful in its efforts. No submissions were received for this work with no options to commence any work on the structures. Following this procurement process the January 2024 minor flood event occurred requiring Council to reassess its position in relation to the long-term life and maintenance requirements of the structures.
It is proposed that the overwater structures as shown in the below diagram are removed from the site by way of demolition. This diagram depicts the structures that will be removed with the western deck being retained to continue to provide protection to the irrigation pump and associated infrastructure.
The below proposal currently excludes the Riverbank Walkway used for disability access to the site. This infrastructure is to be considered in future works and will include consultation on this topic with the community.
Identified Structures Proposed for Removal
Legal IMPLICATIONS
This report and its recommendations are consistent with the following legislative provisions:
Local Law 7 (Local Government Controlled Areas and Roads)
RISK MANAGEMENT IMPLICATIONS
Initially it was determined that repairs to the overwater structures should be undertaken to recover the site to full activation. Following a structural assessment of the infrastructure including costs analysis of different repair options, it was identified that the material used for the structures is deteriorating at a faster rate than originally designed. As more frequent flooding occurs the structures are now exposed to quicker degradation.
Cost analysis to repair or to remove the structures is very similar in cost to demolition. To repair the structures would expose them to further damage in future flooding events. Subsequently, if the structures were to be repaired this cost would be ongoing each time flood inundation occurs at this site.
It was determined that the most cost-effective outcome for Council was to remove these overwater structures to reduce not only the ongoing maintenance and repair costs, but to also provide Council with a more efficient recovery of the site following an inundation event.
Additionally, if future funding from the Queensland Reconstruction Authority (QRA) for this type of asset is no longer offered in the future, the costs to continue to repair this site after future floods will be a cost that Council will need to include in future budgets.
Financial/RESOURCE IMPLICATIONS
The River Heart site was included in submissions for funding under the QRA and was approved. The costs for the removal of the overwater structures can be absorbed within the funding approved by the QRA.
Any proposed works to the Riverbank Walkway will need to be discussed and prioritised under future capital works depending on the outcome of future community consultation on this structure.
COMMUNITY and OTHER CONSULTATION
The removal of the overwater structures will be communicated to the community with details on the basis for the decision including the ongoing degradation of the assets following multiple flood inundation events. This will be undertaken prior to any physical works commencing.
Community consultation and feedback will be sought on the Riverbank Walkway through several communication channels and media to assist in informing any further works to this structure.
A community engagement plan (Attachment 2) has been developed outlining the consultation proposed with the community.
Internal stakeholders who have been engaged support the final recommendation of the River Heart overwater structures include:
(a) General Manager (Asset & Infrastructure Services)
(b) General Manager (Environment & Sustainability)
(c) Asset Services Branch
(d) Flood Recovery Project Team
Several briefings have been held with the Mayor and Divisional Councillors in relation to the details and recommendations for the River Heart overwater structures and the associated community engagement and consultation.
Conclusion
The removal of the River Heart overwater structures, as detailed in this report, will provide a more financially and environmentally sustainable parkland, while also significantly reducing the effort required to reopen the parkland after flooding events.
The removal of the overwater structures will still provide community users with a location adjacent to the river for walking and recreational purposes.
HUMAN RIGHTS IMPLICATIONS
HUMAN RIGHTS IMPACTS |
|
OTHER DECISION |
|
(a) What is the Act/Decision being made? |
That Council endorses the removal of the overwater structures as detailed in this report. This includes the retention of the western deck which provides protection and housing for the irrigation pump and associated infrastructure.
|
(b) What human rights are affected? |
No human rights are affected by this decision. This is because Council has a responsibility to manage the infrastructure and assets the community utilise. The subject of removing the asset will not impact on the human rights of any third parties.
|
(c) How are the human rights limited? |
Not applicable
|
(d) Is there a good reason for limiting the relevant rights? Is the limitation fair and reasonable? |
Not applicable
|
(e) Conclusion |
The decision is consistent with human rights. |
Attachments and Confidential Background Papers
1. |
Community Engagement Plan ⇩ |
|
|
|
CONFIDENTIAL |
2. |
Matthew Mulroney
Program Manager (Flood Recovery CFRCP)
I concur with the recommendations contained in this report.
Matt Anderson
General Manager (Asset and Infrastructure Services)
I concur with the recommendations contained in this report.
Sonia Cooper
Chief Executive Officer
“Together, we proudly enhance the quality of life for our community”
Infrastructure, Planning and Assets Committee Meeting Agenda |
11 June 2024 |
ITEM: 3
SUBJECT: Springfield Central E-Scooter Pilot
AUTHOR: Team Lead (Transport and Traffic)
DATE: 31 May 2024
Executive Summary
This is a report concerning the electric scooter (e-scooter) pilot scheme which is being held in the Springfield Central area. In particular, the report discusses the pilot to date and the proposal to extend the pilot to enable collection of additional data to support Council’s future position for micro-mobility devices across the City.
Recommendation/s
A. That the report be received and the contents noted.
B. That Council approve the extension of the current e-scooter pilot in Springfield Central area for an additional 12 months to 1 July 2025, with the option for an additional 12 month extension if considered necessary.
RELATED PARTIES
There was no declaration of conflict of interest.
ifuture Theme
Vibrant and Growing
Purpose of Report/Background
At the Growth Infrastructure and Waste Committee meeting held on 4 November 2021, Council approved a 6-month pilot of e-scooters in Springfield Central with the possibility of extending the pilot an additional 6-months (refer to Attachment 1 for Item 2 of the Growth, Infrastructure and Waste Committee meeting held 4 November 2021).
In response to the recommendation to proceed with an e-scooter pilot, Council ran an expression of interest (EOI) for micro-mobility companies to lodge their submissions for a pilot program for e-scooters in the Springfield Central area.
Following the EOI process, Beam Mobility was chosen as the successful micro-mobility company to undertake the pilot, which has now been in place since July 2023. The current pilot was originally proposed to be completed by 31 December 2023 but was extended for an additional 6 months. The pilot is now due to be finalised on 1 July 2024.
The key objective of the pilot is to understand the long term viability and inform decision making processes regarding additional micro-mobility services across the Ipswich Local Government Area (LGA). Further to this, Council is seeking to gain insight into key considerations required to support mobility as a service. To date, there have been some encouraging results from the pilot, however it is considered that Council would benefit from an extension of the pilot period to collect additional and sufficient data to determine the longevity of e-scooters in the City.
Other Councils have set much longer pilot periods than what Council currently has in place, and it is now evident that we would also benefit from the collection of additional data. This is to enable a full evaluation of longer term data patterns.
In addition, with the recent announcement by the state government to impose a 50c public transport fare scheme commencing in August 2024, it would be ideal to capture what this means for travel patterns for e-scooters, as it may quite likely increase the demand for trips to public transport hubs.
Recommendation B in the previous report to Council (Attachment 1), outlined “The outcomes of the e-scooter Pilot be reported to a future Growth, Infrastructure and Waste Committee Meeting”.
Given the suggestion that Council has not collected sufficient data from the pilot, the proposed extension will provide more relevant and sufficient data to report back to Council following an extended pilot period, whereby more data and intelligence can be collected.
Pilot Results to date
The e-scooter pilot scheme in Springfield Central has been relatively successful in providing an alternative and sustainable travel mode to the community. Below is a summary of the data captured.
Trip Data Analysis:
For the period of July 2023 to March 2024 inclusive, the following data has been made available:
· Total Trips made – 21,577
· Average trip duration – 12 minutes
· Average trip distance – 2.1 km
· Average 80 trips per day
The current e-scooter trial is showing evidence of:
o recreational usage,
o travel to/from shops,
o travel to/from public transport,
o travel to/from work.
· Public transport is a key destination and continual e-scooter availability may encourage modal shift from car to public transport usage. Other key destinations include shops and the university.
· In Springfield Central, the Robelle Parklands and Orion Shopping Centre are popular destinations for recreational use and are also near public transport and the university. This encourages a positive sustainability outcome.
Safety:
There have not been any Beam related e-scooter safety incidents reported across the operating area for the length of the pilot scheme to date.
Should an issue arise, the micro-mobility company has provided evidence of public liability insurance and are prepared to act, in a quick response time, in the interest of public safety.
Legal IMPLICATIONS
This report and its recommendations are consistent with the following legislative provisions:
Not Applicable
This report is consistent with iFuture, the City of Ipswich Transport Plan (iGO) and iGO Intelligent Transport System Action Plan.
RISK MANAGEMENT IMPLICATIONS
With regard to potential safety risks associated with an increase in e-scooters on the roads and pathways, these have so far been negated. This has been through proper policy and procedures being followed, auditing, monthly meetings, technology advancement and stakeholder engagement.
Some of the community who have made the shift to e-scooter usage will be disadvantaged if the e-scooter pilot is not extended. There may be dissatisfaction (and possibly community backlash) among the community and will more than likely revert users to less desirable transport modes such as cars.
By not extending the pilot, Council may not have enough data to make the best informed decision on the suitability of e-scooters, and subsequently micro-mobility devices with our LGA. This can be mitigated by extending the current pilot and continuing to collect data on the pilot.
Financial/RESOURCE IMPLICATIONS
No capital financial implications exist regarding the e-scooter pilot.
Council officers undertake business as usual activities regarding the e-scooter pilot such as on site auditing of e-scooter operations and regular attendance at stakeholder meetings. This however is covered by normal operational budgets at no additional cost to Council.
COMMUNITY and OTHER CONSULTATION
To date, key stakeholders are asked for comment on the e-scooter pilot scheme every few months. The micro-mobility operator, Council officers and Division 2 Councillor meet for updates regularly and there have been very few complaints received.
There have been no complaints from external stakeholders such as the Queensland Police Service, the Department of Transport and Main Roads and major local businesses.
Internal stakeholders have raised small concerns which were able to be mitigated through further communication between the operators and other Council departments. The issues were addressed promptly and did not affect ongoing operations.
Community feedback to date shows that there has been a low number of negative complaints compared to the number of user trips, with an average of 4 complaints per month and 2,397 trips per month being undertaken.
Conclusion
An e-scooter pilot is currently in place within the Springfield Central area. To enable Council to make a more informed decision on the provision and operation of e-scooters and micro-mobility devices within the City, it would be valuable to extend the existing pilot. This will allow collection and evaluation of data from the current trial and will be subject to a future report back to Council on the proposed long term viability of micro-mobility devices across the City.
HUMAN RIGHTS IMPLICATIONS
HUMAN RIGHTS IMPACTS |
|
OTHER DECISION
|
|
|
|
(a) What is the Act/Decision being made? |
Recommendation B states that Council approve the extension of the current e-scooter pilot in Springfield Central area for an additional 12 months to 1 July 2025, with the option for an additional 12 month extension, if considered necessary
|
(b) What human rights are affected? |
No human rights are affected by this decision
|
(c) How are the human rights limited? |
Not applicable
|
(d) Is there a good reason for limiting the relevant rights? Is the limitation fair and reasonable? |
Not applicable
|
(e) Conclusion |
The decision is consistent with human rights. |
Attachments and Confidential Background Papers
1. |
E-Scooters in Ipswich Report from the Growth
Infrastructure and Waste Committee Meeting held 4 November 2021 ⇩ |
Berto Santana
Team Lead (Transport and Traffic)
I concur with the recommendations contained in this report.
Mary Torres
Infrastructure Strategy and Planning Manager
I concur with the recommendations contained in this report.
Tony Dileo
Manager, Infrastructure Strategy
I concur with the recommendations contained in this report.
Matt Anderson
General Manager (Asset and Infrastructure Services)
“Together, we proudly enhance the quality of life for our community”
Infrastructure Planning and Assets Committee Meeting Agenda |
11 June 2024 |
ITEM: 4
SUBJECT: Asset and Infrastructure Services Department Capital Delivery Report April 2024
AUTHOR: Acting Principal Officer (Program Management)
DATE: 13 March 2024
Executive Summary
This is a report concerning the performance of the capital delivery by the Asset and Infrastructure Services Department for the month of April 2024.
Recommendation/s
That the report on capital delivery by the Asset and Infrastructure Services Department be received and the contents noted.
RELATED PARTIES
There are no known conflicts of interest in relation to this report.
ifuture Theme
Vibrant and Growing
Purpose of Report/Background
The variance for the month is primarily attributed to reduced spending within the Strategic Transport Sub-program, Asset Rehabilitation, and delays in vehicle and plant delivery from the Fleet Capital Program. Significant progress, however, was achieved in the Parks, Sport, and Environment Program, particularly with the projects at Cameron Park, Richardson Park, and the Wiley Street BMX Canteen Upgrades, which have helped contribute to the outcomes for the month.
Whilst the year to date expenditure reached $71.8 million, the variance to the base line budget has increased from the March results of $427k and is now $800k below the year to date budget of $72.6 mil.
The table below shows the baseline for the published budget
and expenditure to date for the 2023-2024 FY.
The April financial outcome, being $6.79 mil of actual expenditure, was largely attributable to the following programs / projects expenditure:
2023-2024 FY Budgeted > $100k:
• Springfield GBA RU Stg 3 $2.9mil • Mary William TL 23 $708k • Redbank Plains Rd Stg 3 RU 17 $496k • Richardson Pk PG 20 $348k • Wiley St BMX Canteen Upgrade $268k • Adelong Av, Thagoona $232k • Blackwood KC 23 $188k • Ripley Rd RU 23 $145k • Cameron Pk UG 20 $143k |
|
|
Key projects underspent against their Baseline budget > $100k:
· Springfield Parkway Stage 2 Budget $1.47mil vs actuals $80k
· Redbank Plns Rd Stg 3 RU 17 Budget $938k vs actuals $496k
· East Ipswich Invest Stage 1 DR Budget $475k vs actuals $41k
· Mowing Minor Plant 23 Budget $300k vs nil spend
· Springfield Pkwy RU 19 Budget $291k vs actuals $61k
· Hiddenvale Road Bridge BR20 Budget $286k vs actuals $99k
· Kirk St LR 23 Budget $110k vs nil spend
· Gravel Resheeting Budget $200k vs actuals $95k
Program Variances (Budget vs Actual)
Asset Rehabilitation overall, achieved an actual spend of $717k resulting in an $900k underspend against an adopted budget of $1.62mil for the month of April.
The majority of the underspend was attributed to delays in receiving drainage materials associated with the East Ipswich Stage 1 Drainage Works.
Due to the extended lead times associated with procuring these materials, prior approval was received to purchase the necessary drainage pipes this FY. This measure aims to mitigate the risk to construction activities for this Grant-funded project identified for delivery within the 24-25FY.
Early works relating to the Energex relocation requirements associated with Hiddenvale Road Bridge replacement also experienced delays impacting the financial results specifically to this sub-program.
Local Amenity incurred an actual spend of $305k against a budget of $112k for the month of April resulting in an overspend of $193k. The majority of the spend was attributed to the continuation of the construction activities associated with the kerb and channel currently underway at Blackwood Avenue.
Flood Mitigation and Drainage incurred an actual spend of $16k against a budget of $30k for the month of April resulting in an underspend of $14k. The spend was primarily a result of re-phasing of planning and design activities associated with Parcell Street drainage investigations.
Transport and Traffic had an underspend of $133k when compared to the adopted budget of $4.80 million for the month. The actual expenditure was very close to the budgeted amount with actual’s amounting to $4.67 million.
Redbank Plains Road Stage 3 has progressed well despite the impact of the transition from Allroads to Council as the Principal contractor on site, still achieving $496k against the original baseline budget of $937k.
The combined expenditure for all three Springfield Parkway Stages stood at $3.04 million, falling short of the baseline budget of $3.32 million. Whilst good results were achieved within Stage 3 Works as a result of bringing forward work, delays associated with Urban Utilities approvals within stage 2 have significantly impacted the final results for the month.
Parks Sports and Environment overall, achieved an actual spend of $813k resulting in an $693k overspend against a budget of $120k for the month of April. The overspend can primarily be attributed to:
Richardson Park incurred expenses of $348,000 during the month, despite having a baseline budget of $0 due to the timing of works. Construction progress is on track, and the contractor aims to complete it by June.
Progress on the grant-funded Cameron Park Upgrade project now has the contractor established on-site, with expenses reaching $142k against a current monthly baseline budget of $0. Delays caused by asbestos in the amenities block impacted the dismantling timeline. According to the latest program, the project remains on track for practical completion in late August.
The Willey Street BMX Canteen Upgrade experienced additional expenses in April due to an increase in scope to meet DDA compliance and Certificate of Occupancy requirements. The project has now achieved practical completion, with actual costs for the month totalling $268k, resulting in a further overspend of $168k against the budget.
Fleet, experienced a $113k spend against a monthly budget of $420k as a result of delays associated with the delivery of vehicles and plant, that had previously been identified for delivery within the month of April.
The delivery of plant associated with minor plant replacements, including mowing minor plant and major plant acquisitions, has been delayed due to shortages across the industry.
Works continue with SmartTrack GPS program which is currently upgrading from 3G to 4G, with work on light vehicles expected to be completed by early June. The remaining fleet, monitored by SmartTrack, should be upgraded by September, subject to component availability and resource allocation.
Summary
In April, the Asset and Infrastructure Services Department Capital Works Program saw an increase in the gap between actual progress and the year-to-date budget. However, the actual expenditure for the month totalled $6.79 million, falling just 5.2% short of the budgeted amount of $7.16 million, a variance of $372k. The cumulative year-to-date expenditure now stands at $71.8 million, slightly below the current budget of $72.6 million.
The main spends above budget for the month were:
· Traffic and Transport Program -
o Springfield GBA RU Stg 3 $2.9 mil
o Mary William TL 23 $708k
o Redbank Plns Rd Stg 3 RU 17 $496k
o Ripley Rd RU 23 $145k
· Parks Sport and Environment
o Richardson Pk PG 20 $348k
o Wiley St BMX Canteen Upgrade $268k
o Cameron Pk UG 20 $143k
· Asset rehabilitation
o Adelong Av, Thagoona $232k
· Local Amenity
o Blackwood KC 23 $188k
The budget variance for the year, initially reported in March as being $430k under, has further increased to $800k below the baseline for the month of April. Although expenditures have generally aligned with the baseline trend, there remain several key projects with substantial planned costs in the coming months that are critical for achieving the desired end-of-year budget results.
Further scrutiny of the carryover requirements identified in April’s forecasting results is currently being assessed to provide transparency for the remaining two months of the financial year and the implications it may have upon the 24-25FY program.
Although there is an optimistic outlook for the program, it is important that the department maintains the necessary oversight of the planned activities to help ensure they are aligned with the department’s strategic objectives as closely as possible, particularly with regards to the known time constraints that exist for the remainder of the financial year.
Major Projects
Springfield Parkway & Springfield-Greenbank Arterial Road Upgrade
A general overview of the project shows good progress being made on all three stages, with the progress best outlined as:
Stage 1: Stage 1 has previously reached practical completion, with only minor defects remaining. While BMD is actively addressing these issues, it has been identified that the landscaping associated with this stage will be excluded from the practical completion milestone due to having had insufficient time for it to establish. The proposal is to hand over these works to the Council and include them in the maintenance requirements as part of Stage 3 Landscaping Works.
Stage 2: The Stage 2 Design has reached the IFC milestone with only service relocation designs remaining. The Project Team is developing a further Early Works Package to accelerate Stage 2, which would allow both service relocations and civil works to start earlier than originally programmed. The project team have been proactive in procuring the necessary Stormwater Pipes, RE Wall Panels and RE Backfill material in preparation for this early works package. The new 3 x 3.6m culverts works have restarted and the design is being modified due to some geotechnical requirements changing. We are we using a cost target variation of $1.2m, which should mitigate risk and avoid the budget being exceeded.
Stage 3: Services relocation are all complete including a successful UU Live connection which is a major milestone for the project. As a result works are now being undertaken across multiple work fronts, with day and night shifts and this is allowing the project to advance quickly. As a result of recent rain, the Exit 32 Off Ramp batter face has deteriorated and with a number of slips occurring. This required temporary remedial works and installation of a concrete barrier. Monitoring continues and a more permanent treatment design is being developed.
The QR Eastern Carpark’s restructuring is nearing practical completion, pending the resolution of minor defects and omissions, and is expected to open in early June. The TMR has processed and approved the initial funding invoice of $3.7 million for prompt payment, and the subsequent invoice of $5.8 million is scheduled for submission by the end of May. Negotiations are underway to secure additional funding, with targets set between $23.0 and $25.0 million ($8.0 to $10.0 million increase).
Generally, overall, the project continues to remain on track with the program being monitored closely to maintain overall milestones and mitigate cost and time delays. Stakeholder Engagement continues to be very well managed by the project site team, ensuring they are proactive in addressing any concerns before they can arise, where possible.
Redbank Plains Road Upgrade
While the transition from Allroads to Council as the Principal Contractor has been gradual, the project is now making good progress. In conjunction with Council’s internal resources, Naric Civil Pty Ltd has been mobilized on-site since mid-April to continue the necessary programming of works. These activities have also utilized the existing panel arrangements where possible for additional resourcing and to facilitate the advancement of the necessary civil works.
Work zones still remain significantly restricted until new traffic management arrangements can be put in place. Once these are resolved, works are expected to accelerate even further. Many areas of partially completed work have forced the entire site footprint to be a work zone under traffic management (which has been a feature for some time). The primary focus remains on completing both the Southern and Northern work zones, aiming to remove traffic controls and signal that the project is nearing completion. The target completion date is currently identified for November this year, dependant on favourable site conditions and weather.
Northern Portion: Retaining wall works located along the eastern side adjacent to Kruger Parade roundabout to Morgan Street continue with posts and sleepers having been installed for these properties. With further works associated with watermain alterations having also been completed for five properties.
Central Zone: Construction of ‘fast lane’ gravels against central median retaining “Wall 1” are underway, with the site currently preparing for the necessary asphalt layers.
Southern Zone: Significant asphalt works have been completed, allowing for a traffic switch. The Verran Street intersection can now commence, including the closure of this Street.
Passenger Transport Accessible Infrastructure Program (PTAIP) - Bus Stop Program
The Program (PTAIP) aims to enhance passenger transport facilities across Queensland, ensuring compliance with the Disability Discrimination Act (DDA) requirements. Funded by the Queensland Government, PTAIP continues to support councils with upgrading the existing bus stops and other transport infrastructure.
The current status for the program consists of:
· Design work for bus stops funded in the current year are now finished. With these projects having been handed over to the Construction team for delivery, with an expected completion before 30th June 2024. This includes Mount Crosby Road (Near Croydon St) which has now been handed over following the design being finalised.
· Design for Lawrie Drive is continuing, as we await response from Urban Utilities for their impact assessment which will result in construction being scheduled for FY2024-2025.
· The remaining stops with grant funding will be constructed in FY2024-2025. Designs for these locations, including Booval Station, Brisbane Street (Near Keogh St), Workshops Street (At Sutton Park), and Blackstone Rd (Near Whitehill Rd), will be finalised by the end of the financial year.
· Council is
progressing with the bus stop upgrade on Reif Street, originally funded
under the 2022-2023FY PTAIP program. TransLink
has granted an extension until
30 June 2024 for necessary consultations and approvals with Urban
Utilities.
Grant Projects Scheduled
for delivery this FY (includes Multi-year Funding)
NOTE: Below table includes reporting on capital construction
projects only – it does not include Design Only or Operational projects.
Grant Amount |
Total estimate Project Cost |
Required Project Completion Date / Agreement End Date |
Project Status |
|
(Cycle Network Local Government Grants Program (CNLGGP) |
State Funded |
|||
Deebing Creek Stage 2 (Design Component) |
$ 75,000.00 |
$ 250,000.00 |
30/06/2023 |
Complete |
Deebing Creek Stage 2 (Construction) |
|
|
|
Submitted for consideration |
Brassall Bikeway Data Counters |
$ 85,000.00 |
$ 140,000.00 |
30/06/2024 |
Complete |
Civic Centre Carpark EOT (Tulmur Place EOT Facility) |
$ 194,000.00 |
$ 388,000.00 |
30/06/2024 |
In progress |
Queen Vic Pde Construct (Eastern Ipswich Link Stage 2) |
$ 750,000.00 |
$ 1,500,000.00 |
30/06/2024 |
In progress |
Election Commitment 2020 (Dept Tourism, Innovation and Sport) |
State Funded |
|||
Jim Donald Raceview Clubhouse |
$ 900,000.00 |
$ 1,510,000.00 |
31/01/2024 |
Complete |
BMX Clubhouse Wiley Park |
$ 500,000.00 |
$ 1,496,000.00 |
30/03/2024 |
Complete |
TIDS (Transport Infrastructure Development Scheme) |
State Funded |
|||
Springfield Greenbank Arterial (Stage 3) |
$ 196,145.00 |
$ 11,600,000.00 |
30/06/2025 |
In progress |
Bus Stop Shelter Program 2022-23 (BSSP) |
State Funded |
|||
Various
Note – Reif Street Project is tied to BSSP as well as PTAIP – Approval received with extension of time until 30-6-24 |
$ 152,000.00 |
$ 152,000.00 |
31/12/2024 |
Complete (except 1) |
|
|
|
In Progress |
|
Passenger Transport Infrastructure Grants 2022-23 (PTAIP) |
State Funded |
|||
Various |
$ 293,475.00 |
$ 319,725.00 |
30/09/2023 |
Complete (except 1) |
Note – Reif Street comment as noted above in BSSP
|
|
|
30/06/2024 |
In Progress |
Local Roads & Community Infrastructure Program (LRCIP) |
Federal Funded |
|||
Alice Street Kerb and Channel |
$ 1,500,000.00 |
$ 1,870,000.00 |
30/06/2024 |
Complete |
South Station Road A Road Rehabilitation |
$ 1,000,000.00 |
$ 1,870,000.00 |
30/06/2024 |
Complete |
Charlotte Street Road Rehabilitation |
$ 1,200,720.00 |
$ 1,450,000.00 |
30/06/2024 |
Complete |
Nolan Street Road Rehabilitation |
$ 955,000.00 |
$ 1,010,000.00 |
30/06/2024 |
Complete |
Adelong Avenue, Culvert Rehabilitation |
$ 671,381.00 |
$ 950,000.00 |
30/06/2024 |
In Progress |
Tallegalla Road, Culvert Rehabilitation |
$ 671,381.00 |
$ 935,000.00 |
30/12/2024 |
In Progress |
R2R (Roads to Recovery) |
Federal Funded |
|||
Springfield Parkway |
$ 2,327,860.00 |
$ 10,000,000.00 |
30/06/2025 |
In progress |
South East Queensland Community Stimulus Package (SEQCSP) |
State Funded |
|||
Cameron Park Playground and Amenities Upgrade |
$ 2,000,000.00 |
$ 3,282,349.00 |
EOT Requested until 26/08/24 |
In progress |
Richardson Park Playground and Amenities Upgrade |
$ 1,500,000.00 |
$ 2,232,000.00 |
30/06/2024 |
In progress |
Bridges Renewal Program 2022-2024 |
Federal Funded |
|||
Hiddenvale Road, Calvert |
$ 3,901,761.00 |
$ 4,877,201.00 |
30/09/2024 |
In progress |
Keanes Road, Calvert |
$ 1,747,860.00 |
$ 2,184,825.00 |
30/09/2024 |
Complete |
Purga School Road, Purga |
$ 5,000,000.00 |
$ 8,185,876.00 |
|
Submitted for consideration |
Federal Funded |
||||
Purga School Road, Purga |
$ 3,904,203.00 |
$ 4,880,254.00 |
|
Submitted for consideration |
Australian Cricket Infrastructure Fund |
Other |
|||
Ivor Marsden Sports field Lighting Upgrade |
$ 100,000.00 |
$ 907,500.00 |
N/A |
In progress |
Blackspot Program 2023-2024 |
Federal Funded |
|||
Old Logan Road and Formation Street, Carole Park |
$ 65,500.00 |
$ 65,500.00 |
30/06/2024 |
In progress |
Robertson Road and Whitehill Road, Eastern Heights |
$ 694,000.00 |
$ 694,000.00 |
30/06/2025 |
In progress |
Gordon Street and South Street, Ipswich |
$ 92,000.00 |
$ 92,000.00 |
30/06/2024 |
In progress |
School Transport Infrastructure Program |
State Funded |
|||
WMAC Signals Wulkuraka |
$ 198,000.00 |
$ 396,000.00 |
30/06/2024 |
Not yet started |
Flexible Funding Grants |
State Funded |
|
|
|
Karalee Alternate Access Track |
$ 50,000.00 |
$ 55,000.00 |
30/12/2024 |
In progress |
Priority Infrastructure Projects |
State Funded |
|
|
|
Ash Barty Park Upgrade |
$ 525,000.00 |
$ 525,000.00 |
28/02/2025 |
In progress |
Master Schedule status of Practical Completion milestone for April
(Exclusive of emergent projects)
Milestone |
April Actual |
Actuals Year to date |
Target for 23/24 |
Practical Completion |
0 |
30 |
37 |
As at end of April, project completion status shows 30 projects have
reached practical completion from a total of 37 projects that are scheduled for
delivery this FY.
Current status of Construction projects for 2023-2024 FY
Current Status of Projects |
Count of Projects February |
|
|
Concept Design |
0 |
Detail Design |
1 |
Handed Over for Execution |
2 |
Construction in Progress |
4 |
Practically Complete |
30 |
The data shown above for status of projects scheduled for delivery in the 2023-2024 FY. Majority of projects scheduled for delivery this financial year have been designed and handed over for construction, with only 1 project yet to be handed over to construction.
Legal IMPLICATIONS
This report and its recommendations are consistent with the following legislative provisions:
Local Government Act 2009
policy implications
Nil
RISK MANAGEMENT IMPLICATIONS
The Asset and Infrastructure Services Department has a departmental risk register that includes the delivery of the capital program. The leadership team of the department continues to monitor our risk in relation to this and takes mitigation action where necessary.
Financial/RESOURCE IMPLICATIONS
No financial / resource implications.
COMMUNITY and OTHER CONSULTATION
No community consultation was required in relation to this report.
The Stakeholder Management Branch of the Asset and Infrastructure Services Department engages extensively with the community impacted by our works to ensure that they are informed in advance of works, communicated with during works and ensure that any issues that arise are managed effectively.
Conclusion
The Asset and Infrastructure Services Department is committed to delivering high quality infrastructure for the community.
HUMAN RIGHTS IMPLICATIONS
HUMAN RIGHTS IMPACTS |
RECEIVE AND NOTE REPORT |
Attachments and Confidential Background Papers
1. |
Asset Rehabilitation Report ⇩ |
2. |
Capital Delivery Report April 2024 ⇩ |
Tom Reynolds
Acting Principal Officer (Program Management)
I concur with the recommendations contained in this report.
Graeme Martin
Manager, Capital Program Delivery
I concur with the recommendations contained in this report.
Matt Anderson
General Manager (Asset and Infrastructure Services)
“Together, we proudly enhance the quality of life for our community”
Infrastructure, Planning and Assets Committee Meeting Agenda |
11 June 2024 |
ITEM: 5
SUBJECT: Planning and Environment Court Action Status Report
AUTHOR: Manager, Development Planning
DATE: 27 May 2024
Executive Summary
This is a report concerning a status update with respect to current court actions associated with development planning applications.
Recommendation/s
That the Planning and Environment Court Action status report be received and the contents noted.
RELATED PARTIES
The related parties, being the appellants associated with any court actions, are detailed in the attachment to this report.
ifuture Theme
Vibrant and Growing
Safe, Inclusive and Creative
Natural and Sustainable
A Trusted and Leading Organisation
Purpose of Report/Background
Whilst this report outlines a specific list of development application related court actions, from time to time, Council will be engaged in prosecutions relating to development offences and other matters. Owing to the nature of these prosecutions, these matters are not generally listed in the attached court action report. However substantial matters will be presented to the Growth, Infrastructure and Waste Committee using this report from time to time.
Further information on these appeals can be found on the Planning and Environment Court web site.
Legal IMPLICATIONS
This report and its recommendations are consistent with the following legislative provisions:
Local Government Act 2009
Planning Act 2016
Planning Regulation 2017
policy implications
N/A
RISK MANAGEMENT IMPLICATIONS
There are no risk management implications associated with this report.
Financial/RESOURCE IMPLICATIONS
N/A
COMMUNITY and OTHER CONSULTATION
The contents of this report did not require any community consultation.
Conclusion
The Planning and Regulatory Services Department are currently involved with several Planning and Environment Court and Supreme Court matters. Attachment 1 to this report provides a current status with respect to these matters.
HUMAN RIGHTS IMPLICATIONS
HUMAN RIGHTS IMPACTS |
RECEIVE AND NOTE REPORT |
The recommendation states that the report be received and the contents noted. The decision to receive and note the report does not limit human rights. Therefore, the decision is compatible with human rights. |
Attachments and Confidential Background Papers
1. |
Planning and Environment Court Action Status Report ⇩ |
Greg Potter
Manager, Development Planning
I concur with the recommendations contained in this report.
Brett Davey
General Manager (Planning and Regulatory Services)
“Together, we proudly enhance the quality of life for our community”
Infrastructure, Planning and Assets Committee Meeting Agenda |
11 June 2024 |
ITEM: 6
SUBJECT: Exercise of Delegation Report
AUTHOR: Manager, Development Planning
DATE: 27 May 2024
Executive Summary
This is a report concerning applications that have been determined by delegated authority for the period 3 May 2024 to 27 May 2024.
Recommendation/s
That the Exercise of Delegation report for the period 3 May 2024 to 27 May 2024, be received and the contents noted.
RELATED PARTIES
There are no related parties associated with the recommendation as the development applications have already been determined.
ifuture Theme
A Trusted and Leading Organisation
Purpose of Report/Background
The following delegations (and associated sub-delegations) contain a requirement for the noting of applications determined by delegated authority:
· Approval of Plans for Springfield
· Determination of Development Applications, Precinct Plans, Area Development Plans and Related Matters
· Exercise the Powers of Council under the Economic Development Act 2012
· Implementation of the Planning and Development Program
· Exercise the Powers of Council under the Planning Act 2016
Legal IMPLICATIONS
This report and its recommendations are consistent with the following legislative provisions:
Local Government Act 2009
Planning Act 2016
Planning Regulation 2017
policy implications
N/A
RISK MANAGEMENT IMPLICATIONS
There are no risk management implications associated with this report.
Financial/RESOURCE IMPLICATIONS
There are no resourcing or budget implications associated with this report.
COMMUNITY and OTHER CONSULTATION
The contents of this report did not require any community consultation. In the event that the development applications listed in this report triggered ‘impact assessment’ pursuant to the Ipswich Planning Scheme, public notification was undertaken as part of the development application process in accordance with any legislative requirements and matters raised in any submissions and were addressed in the respective development assessment reports.
Conclusion
The Planning and Regulatory
Services Department is responsible for the assessment and determination of
development applications. Attachment 1 to this report provides a list of
development applications that were determined by delegated authority for the
period
3 May 2024 to 27 May 2024.
HUMAN RIGHTS IMPLICATIONS
HUMAN RIGHTS IMPACTS |
RECEIVE AND NOTE REPORT |
The Recommendation states that the report be received and the contents noted. The decision to receive and note the report does not limit human rights. Therefore, the decision is compatible with human rights. |
Attachments and Confidential Background Papers
1. |
Exercise of Delegation Report ⇩ |
Greg Potter
Manager, Development Planning
I concur with the recommendations contained in this report.
Brett Davey
General Manager (Planning and Regulatory Services)
“Together, we proudly enhance the quality of life for our community”